Mercedes-Benz Warehouse, Silverstone
About this project
Jumbo Stud Ltd were asked to create a high bay dividing jumbo stud wall partitions to split the warehouse into two units.
The client's requirement for a 60-minute fire-rated jumbo stuff partition was the perfect match for our flagship system, the F60 Jumbo Stud.
- Fermacell board was used to clad this nearly 15m height partition to maintain fire rating.
- Over 70 linear metres of this 15m Jumbo Stud wall partition was built in 4 weeks.
- Fully skimmed, ready for decoration.
- Heavy gauge SFS metal frame system to match the desired height.